NOTE: Total construction time averages 3 - 9 months with 3 - 6 months being ideal.
The first step to building your casita is creating building plans. You can hire an architect to create these or browse the City's digital Casita Permit-Ready Plan Library. Permit-ready plans include casita floor plan designs and 80% building plans. This can save you time and money. View the Casita Permit-Ready Plan Library.
To build a casita, you may need a loan to help pay for casita construction. It is important to find a loan that fits your budget. The City provides information on different banks' casita financing tools. For these resources, see Financing a Casita.
During the same time that you find a loan, you can also look for a contractor. Hiring a contractor is crucial to building a casita. A contractor will ensure your casita is built safely and correctly. They can also act as your project manager. They can make sure you have the right permits and construction is on-schedule. For guidance on choosing a contractor, plus a list of registered contractors, see Finding a Casita Contractor.
Once you have casita plans, you will need to apply for a residential building permit with the City's Development Services Department (DSD).
You may also need other permits for things like electrical, mechanical, or plumbing. For more information, visit the DSD website or call 210-207-1111.
Construction project management involves supervising and directing a project's stages. Managing casita construction is time-consuming, so many people hire a project manager. A project manager might be a contractor or another professional. For more information on hiring a City-recommended contractor, see our Casita Contractor List.
Casitas are allowed in most residential zoning districts. Zoning is the legal use of land and a zoning district says how a property can be used. For zoning and permitting processes casitas are called Accessory Dwelling Units or ADUs.
Find out more about zoning restrictions and the steps to get a permit: Apply for an ADU Permit
For tips on construction and hiring a contractor, see Finding a Casita Contractor.
If the casita will share a meter with the main house, you will not need a new address for the casita. Instead, the casita address will fall under the main house address.
If you want your casita to have a separate meter, you will need an address to set up new utility connections. To submit a request for an address, you can complete a Request of Address Assignment/Verification (PDF) form online.
You can also complete this form in person at the DSD Office:
Cliff Morton Development and Business Services Center (One Stop) 1901 S. Alamo St. San Antonio, TX 78204 Directions
Information about visiting the One Stop office.